Project description:

The scope of Work includes the successful construction of a 4.6km long Jetty Trestle, including 5 berthing platforms, and a 1.4km quay wall structure (called the MOF), including mooring and berthing equipment and some additional facilities such as Dry dock and Floating Pontoons.

Subcon was awarded the scope of work for the scour protection around the MOF.

OI’s scope of work:

Subcon has contracted OI to provide the Project Engineering and Drafting for the scour protection around the MOF:

  • Assist in the design of concrete mattresses
  • Concrete mattress fabrication mould design
  • Inspection & Test Plans
  • 3D models for mattresses and fabrication moulds
  • 2D AutoCAD general arrangements and details

.