ANMA Offshore Wind - Offshore Cable Installation

Tramontana

Project description:

LS Marine Solution (LSMS) will develop the cable scope for Project Anma, an offshore wind farm near Anma Island in Yeonggwang-gun, Jeollanam-do. Water depths vary from 16.1m to 28.6m MSL across the site. The lowest water depth exists near the east of the project site with 3.2m MSL, and the water depth gently increases as it gets further from the east.

OI has been subcontracted by Tramontana engineering for:

  • Engineering for export cable installation:
  • Cable lay, laydown and recovery
  • Pull-in analysis
  • On-bottom stability
  • Free-span analysis
  • Method statements and procedures for these operations
  • Rigging drawings and storyboards
  • Static and dynamic analysis to make lay tables and workability assessment
Share this page

Related projects

 
N-Sea

PJ00314 OneDyas/Riffgat (2024) Field Engineer

See project
 
Crowley

RAMS support for Transport Lift (2025)

See project
 
N-Sea

One Dyas Cable installation

See project
Back to top