Dos Bocas (2023) Lifting Plan

Van Oord

Project description:

Dos Bocas consists of 3 PLEM installation. The PLEMs are a part of 3 pipelines connecting a refinery to 3 SPM buoys for offloading and loading of hydrocarbons to the FPSOs.

OI’s scope of work :

Part of the main scope that was developing the method statements, OI provided Van Oord with storyboards, lifting plans, rigging arrangements, fabrication drawings, anchor patterns and seafastening drawings.

Share this page

Related projects

 
Seaway 7

Formosa 2 OWF (2022) Project/Field Engineering for Installation of OWF Foundations

See project
 
Wintershall

Carbon Capture Pipelines Pre-FEED

See project
 
Veegeo

Onshore Thermal Drilling Project - Drafting Support

See project