Project description:

VBMS has approached Auxilium to test its cable grapper. The work consisted of:

  • Seabed preparation procedures
  • ROV procedures
  • Clamp installation and cable retrieval procedures
  • Design of the cable clamp

OI’s scope of work:

OI performed (on behalf of Auxilium) the structural verification of the cable clamp:

  • FEM Analysis of cable clamp in ANSYS.