IJMUIDEN VER (2024) Project Engineering Support

VLST

Project description:
Prysmian Group was awarded from TenneT for EPCI of the export cable bundles for IJmuiden Ver Alpha and Nederwiek1 projects. Alpha and Nederwiek1 export cables will be installed onshore, in the Veerse Meer (Inshore route) and offshore.

OI’s scope of work:
OI’s Project Engineers were assigned with developing the following documentation:

  • HDD Installation Procedure
  • HDD Method Statement
  • HDD Sinking Analysis
  • Associated storyboards

Service(s)

Share this page

Related projects

 
Allseas

Structural FEM Support

See project
 
Petrogas

Petrogas E&P – HELM decommissioning (2021) Decommissioning Support

See project
 
Seaway 7

Hollandse Kust Zuid (2022) Project Representative

See project