PLV upgrade & commissioning Pipeline Installation Engineering - Pipe stacking

Undisclosed client

Project description:

Commissioning of pipelay vessel to lay 48” rigid pipeline. Project focus is on vessel modifications and subsequent pipeline installation.

OI’s scope of work:

Main deck strength assessment in way of pipe stacking pillars

  • This study was performed in order to verify capacity of the main deck in pipe storage area. The pipes were stacked at the mid of the ship on the main deck: