Hollandse Kust Zuid (2022) Field Engineer for Monopile installation

Seaway 7

Project description:

Hollandse Kust Zuid is a wind park in front of Scheveningen. During this work, monopiles were transported from Maasvlakte harbor to the wind park site and subsequently driven into the soil using an impact hammer.

OI’s scope of work:

Field engineer tasks:

  • Assist during loadout
  • Check pile hole/gripper arm clashes
  • Log rigging usage
  • Prepare navigation lights
  • Count hammer blows
  • Monitor noise
  • Distribute as-built documentation
  • Check damages
  • Design solutions to improve operation

 