Seagreen OWF (2021-2023) Marshalling Yard Engineer at Nigg

Seaway 7

Project description:

Ensure that jackets were loaded to the cargo barges as per client requirements.

OI’s scope of work:

OI had a representative on-site, at Nigg yard, Scotland. His responsibility was to ensure that the load-out of the jackets onto the cargo barges went as planned and according to procedure. This included, but not limited to:

  • Ensuring correct positioning of the jackets in the grillage and proper welding procedures;
  • Necessary equipment was onboard for the off-shore crew to install the jacket;
  • The ballasting of the cargo barge was done properly to ensued that the barge was levelled;
  • All necessary documentation was in place before sail away.
Share this page

Related projects

 
Undisclosed client

Munmu Baran (2022) Floating Wind Turbine Installation Analysis

See project
 
Tramontana

Fengmiao OWF Export Cable Analysis (2023)

See project
 
RTA Offshore

Umbilical Load Out Analysis, Moss Norway

See project
Back to top