Seagreen OWF (2021-2023) Marshalling Yard Engineer at Nigg

Seaway 7

Project description:

Ensure that jackets were loaded to the cargo barges as per client requirements.

OI’s scope of work:

OI had a representative on-site, at Nigg yard, Scotland. His responsibility was to ensure that the load-out of the jackets onto the cargo barges went as planned and according to procedure. This included, but not limited to:

  • Ensuring correct positioning of the jackets in the grillage and proper welding procedures;
  • Necessary equipment was onboard for the off-shore crew to install the jacket;
  • The ballasting of the cargo barge was done properly to ensued that the barge was levelled;
  • All necessary documentation was in place before sail away.
Share this page

Related projects

 
N-Sea

Drafting support for Subsea Clamp Installation

See project
 
VBMS

Offpipe Support

See project
 
VBMS

Cable Basket and Lift Spreader Design Engineering Support

See project
Back to top