Project description:

Petrol Ofisi is Turkey’s leading fuel, LPG distribution company.

The Antalya Terminal subsea steel fuel pipeline will be extended with hoses app 100 m to realize unloading  from board (centerline) instead of stern (back side).  The detailed design had to be verified.

OI’s scope of work:

  • Control and verify of the design
  • Verifying of concrete block weight
  • Selection of Type of vale that will be installed subsea
  • Location of concrete blocks
  • Connection point of hose with the concrete block