Project description:

Hyundai Engineering & Steel Industries (HESI) is planning to install the monopile (MP) foundations of the Jeonnam I Offshore Wind Farm (JN1). The offshore wind farm comprises of 10 wind turbine generators (WTG) with a total capacity of 100 MW. JN1 is about 130km away from Songdo port, at water depths from 10 up to 30 meters.

This project aims at complementing the performed structural analysis on MPs during upending/lifting operations.

OI’s scope of work:

This work consisted in a complete structural analysis of the MP integrity for 0, 30, 60, 90 deg upending angle. In particular, it included 3 studies:

  1. Linear-elastic analysis
  2. Plastic analysis
  3. Buckling analysis
Share this page

Related projects

 
Seaway 7

Hollandse Kust Zuid (2022) Field Engineer for Monopile installation

See project
 
RTA Offshore

Umbilical Load Out Analysis, Moss Norway

See project
 
DEME Offshore

Norfolk - Export Cable support

See project
Back to top