Greenlink/Formosa 2 (2022) Project Engineering Various Projects

Jan de Nul

Project description:

Office based work for the first four months of the work for Jan de Nul. The original plan was to work as a Project Engineer for the Greenlink project. Due to delays in the project, this scope changed to various projects within Jan de Nul.

OI’s scope of work:

First part, consisted of research & study of the average fuel consumption of the cable lay vessels at JDN. Gathered data from previous years provided JDN a better understanding of it’s vessels fuel consumption, allowing for more accurate future tenders.

In the second part, OI engineer was assigned as a project engineer for a repair scope in Greater Changhua OWF, using Willem de Vlamingh as the work vessel. This consisted in:

  • Develop and write the RAMS (Risk Assessed Method Statements);
  • Develop task plans and story boards;
  • Working together with analysis team to assess feasibility of the work;
  • Project planning and schedule;
  • Logistics.

Project description:

Vessel based work. After the first months of office based work, OI engineer joined Connector vessel, as a project engineer.

OI’s scope of work:

The roles of the project engineer onboard the vessel consisted of:

  • Client and MWS interface;
  • Ensure the crew follow the RAMS as intended;
  • Ensure QA/QC standards are met;
  • MOCs development;
  • Crew changes planning and logistics;
  • Vessel planning: maximizing the vessel working time in an environment were the planning is constantly changing (clients needs, other vessels in the field, weather, etc.);
  • Vessel logistics, ensuring all material necessary for the job is available, port calls, purchases, subcontractors, etc.;

 

 

Share this page

Related projects

 
South Stream

Safety Critical Element Register

See project
 
Van Oord

Guyana (2023) Heads Design

See project
 
Undisclosed client

Munmu Baran (2022) Floating Wind Turbine Installation Analysis

See project
Back to top