J-Tube Lifting Analysis (2023)

Bluestream

Project description:

Bluestream contracted OI to perform Rigging, Clearance and Lifting Analysis of a 2-part J-tube for a n existing platform.

OI’s scope of work:

  • Develop StadPro model to statically check the members in the Bluestream designed rigging.
  • Carry out clearance and clash checks for the proposed pull-in winch location
  • Carry out dynamic analysis of the upper and lower J-tube sections including steps:
  • Above seabed,
  • Upending
  • Load transfer
  • Winch pull-in
  • DAF validation against applied DNV DAFs used in static rigging checks.
Share this page

Related projects

 
Crowley

RAMS support for Transport Lift (2025)

See project
 
DEME Offshore

IJmuiden Ver

See project
 
Seaway7

Seagreen 2 OWF FEM Engineering Support

See project
Back to top