Doggerbank OWF (2022-2023) Inter Array Cable and Export Cable Installation Analysis

DEME Offshore

Project description:

DEME offshore requested assistance for the cable lay installation analysis for the inter-array cables and export cables for the Doggerbank A and B offshore wind farm using DP2 vessel Viking Neptun.

OI’s scope of work:

  • Freelay analysis
  • A&R analysis
  • Survival analysis
  • 1st end pull-in analysis
  • 2nd end pull-in analysis
  • Reporting