Doggerbank OWF (2022-2023) Inter Array Cable and Export Cable Installation Analysis

DEME Offshore

Project description:

DEME offshore requested assistance for the cable lay installation analysis for the inter-array cables and export cables for the Doggerbank A and B offshore wind farm using DP2 vessel Viking Neptun.

OI’s scope of work:

  • Freelay analysis
  • A&R analysis
  • Survival analysis
  • 1st end pull-in analysis
  • 2nd end pull-in analysis
  • Reporting
Share this page

Related projects

 
Van Oord

Mozambiques LNG Umbilical Mooring Analysis

See project
 
SPT Offshore

Projects based in South China sea and in the Gulf of Mexico Structural Engineering

See project
 
N-Sea

Mobilisation Cable repair vessel

See project
Back to top