Baltic Power HDD Scope

DEME

Project description:
The Baltic Power Offshore Windfarm project is located in the Polish Exclusive Economic Zone (EEZ) of the Baltic Sea, approximately 22 km from the Polish coast. The project is a joint venture between PKN and Northland Power, with the goal of developing a 1140 MW wind park.

  • OI’s scope of work:
    Provide project engineering support onshore & field, preparing method statements.
    Procedures:
  • Crew Transfer Procedure
  • Fuel and Bunkering Procedure
  • Diving Method Statement
  • Marine Operations Procedure

Permit support with local authorities:

  • Maritime Office
  • Forestry
  • General Directorate for Environmental Protection (RDOŚ)
  • Procurement, arrangements in ports and with agent
  • Supervision over the mobilisation and execution of the project
Share this page

Related projects

 
Bluestream

Caisson Decommissioning for K12CC, K12, G14-B platforms

See project
 
HESI

JOWP - Monopile integrity analysis during lifting/upending operations

See project
 
Boskalis

Hollandse Kust West Beta

See project
Back to top