Project description:

  • Upgrade and commissioning of Pipelay Vessel to lay approx. 100 km of rigid pipeline
  • Subsequent installation engineering for the pipelay scope

OI’s Engineering services related to PLV upgrade and commissioning:

  • Engineering management of upgrades
  • Crane upgrade
  • Stinger upgrade
  • Firing line upgrade
  • Procurement services of vessel components and project items
  • Engineering related to vessel trials
  • Positioning trials
  • Winch testing
  • Crane load testing
  • Pipeline tensioner load testing
  • Vessel Class approval

.