OI performed due diligence on the project, focusing on the schedule and the accuracy of CAPEX and OPEX, as the end customer wished to verify the financial model against asset values described in over 300 documents. OI applied a structured approach to identify the most valuable sources of information and performed targeted analyses on the most influential asset components. The scope includes:

  1. Project Scope and Definition
  2. Design Engineering Studies
  3. CO2 Stream Quality and Conditions
  4. Flow Assurance Studies
  5. Existing Pipeline Assessment
  6. Surface Facilities Technical and Cost Specifications
  7. Reutilization and Abandonment Plans
  8. Project Schedule and Critical Path Analysis