Project description:

Seaway 7 is responsible for the transportation of the foundations (suction bucket caissons) and jacket support structures for Seagreen OWF. The Seagreen OWF comprises 114 WTG to be located in Scotland.  Two different transportations will be carried out (long-haul – from the fabrication yard to the marshalling yard; short-haul – from to marshalling yard to the offshore installation site).

Seaway 7 has requested Offshore Independents to provide FEM engineering support for the Seagreen Project.

OI’s scope of work:

Offshore Independents provided FEM Engineering for HTV Grillage and Sea Fastening Design.