Ostwind 2 - Engineering Support

Boskalis

Project description:

Boskalis has been awarded the export cable installation contract for the Ostwind 2 offshore grid connection. The contract scope comprises of design and installation of approximately 270 kilometer export cable that will connect the planned Arcadis Ost 1 and Baltic Eagle offshore wind farms to the onshore substation in Lubmin, Germany. The project is expected to commence in 2019 with a planned completion late 2022.

OI's scope of work:

ARC’s scope of work:

Boskalis has contracted ARC to provide the following:

Prepare procedures related to the:

  • Anchor Handling Operations
  • Cable Installation and Burial
  • Sea Trial Operations
  • Cable burial

Prepare Method Statements for Permit Application:

  • Cable Installation and Burial in the 12nM zone
  • Cable Installation and Burial in the EEZ zone

Prepare As-Built Documentation:

  • Cable Loading Report
  • Cable Installation and Burial
  • Mattress Installation at crossings
Share this page

Related projects

 
Seaway 7

Hollandse Kust Zuid (2022) Project Representative

See project
 
Boskalis

L10 -C, -D and -G Decommissioning Project Engineering

See project
 
Van Oord

Guyana (2023) Heads Design

See project
Back to top