Moray East - Engineering and Cable Installation Support

DEME Offshore

Project description:

MOWEL is developing the Moray East Offshore Wind Farm, located off the Scottish coast. The Moray East OWF capacity will be approx. 950MW. Deme has been awarded the EPCI scope for the 100 wind turbine foundations and 3 offshore substation foundations. Also was also tasked to install 100 66kV inter-array cables and two offshore substation interconnector cables.

DEME has contracted ARC to provide the Works Manager and Sen. Field Engineer for the Inter-array & Interconnector cable installation:

  • Providing guidance to project engineers during development of cable installation methodology and procedures
  • Operations optimisation resulting in significant time reduction during cable lay and pull-in on the Living Stone (approx. 10%)
  • Mobilization of CLV & SOV
  • Managing project procurement, logistics and interfaces
  • OCM responsible for SOV personnel and operations including field engineers, WROV / surveyors, HSE and tower teams.

.

Share this page

Related projects

 
N-Sea

Drafting support for Subsea Clamp Installation

See project
 
SPT Offshore

F3-FA Topside Removal Structural Engineering Support

See project
 
SPT Offshore

BOP foundations Installation Engineering

See project
Back to top