Project description:

Boskalis was awarded the infield cable replacement including burial, termination & testing for Hornsrev HR3

OI’s scope of work:

Boskalis Subsea Cables subcontracted OI for the following tasks:

  • Engineering support with delivery of procedures and replying on comments by Vattenfall.Prepare cable trans-spooling work method / procedure
  • A shift offshore on the BOKA Spirit from mid May – beginning June. Concluded by closeout work.