Project description:
Boskalis was awarded the stabilisation of the Cable Protection System (CPS) installed on the infield cables exiting the monopiles of the Sandbank & Hornsrev 3 (HR3) Offshore Wind Farms.

OI’s scope of work:
Boskalis Subsea Cables subcontracted OI for the following tasks:

  • Site visit for rock bag mock-up/test lift at rock bag manufacturer premises.
  • Office-based engineering support including delivery of rock bags installation procedure / method statement, deck layouts etc. and liaison with the Client (Vattenfall).
  • Offshore Field Engineering support on board the Offshore Support Vessel (OSV) North Sea Giant from late February – late April. Concluded by closeout work.
Share this page

Related projects

 
Tideway

Hornsea Export Cable Platform Pull in Analysis

See project
 
Heerema Marine Contractors

Liwan & Ichthys Expert Engineering Support

See project
 
Heerema Marine Contractors

Shell Bonga Riser Installation Study

See project
Back to top