CPS stabilization - Rock bag installation

Boskalis

Project description:
Boskalis was awarded the stabilisation of the Cable Protection System (CPS) installed on the infield cables exiting the monopiles of the Sandbank & Hornsrev 3 (HR3) Offshore Wind Farms.

OI’s scope of work:
Boskalis Subsea Cables subcontracted OI for the following tasks:

  • Site visit for rock bag mock-up/test lift at rock bag manufacturer premises.
  • Office-based engineering support including delivery of rock bags installation procedure / method statement, deck layouts etc. and liaison with the Client (Vattenfall).
  • Offshore Field Engineering support on board the Offshore Support Vessel (OSV) North Sea Giant from late February – late April. Concluded by closeout work.
Share this page

Related projects

 
Seaway 7

Seagreen OWF Suction Caisson Jacket foundations installation (2022) Geotechnical Engineer (Client Rep. o/b Saipem 7000)

See project
 
DEME Offshore

Arcadis Ost - Project engineer onshore and offshore

See project
 
Seaway7

Formosa 2 OWF Engineering Support for Pile Installation Frame design

See project
Back to top