Project description:
TenneT has subcontracted Bluestream for the subsea installation portion for the ICCP retrofit of the SylWin Alpha jacket, located in the German sector of the Southern North Sea / German Bight. The position of the SylWin alpha platform is shown and marked within the red circle as can be seen in the figure.

  • OI’s scope of work:
    Bluestream subcontracted OI for the following tasks:
    Feasibility studies for cable installation
    Providing engineering support for:
    Static cable lay anlaysis
    Dynamic cable lay analysis
    On-bottom stability analysis