Project description:
- IAC CPS require temporary stabilisation via means of rock bags (8Te bags required at all locations)
- Transport the Rockbags offshore and wet store them locally to final position. Final positioning will take place later when the IAC have been installed.
- SW7 has nominated the Island Performer to execute this scope
OI’s scope of work:
- Mobilisation sea fastening deck plan.
- Sea fastening arrangement drawing.
- Corral Sea fastening Arrangement.
- Vessel Corral Deck Plan/General Deck Plan.