Project description:
Empire Wind 1 is the first phase of an offshore wind farm located offshore New York, with an installed capacity of up to 810 MW. Nexans subcontracted Bluestream (now OEG) for the offshore installation of the midshore section of the project, including the lay of two submarine export cables (highlighted in blue) and the execution of jointing between the nearshore and midshore sections. Operations were performed using the K10031 Barge.
OI’s scope of work:
Cable Lay:
- Mobilisation & Seatrials NL
- Transit towing
- Cable Loadout;
- Cable Installation;
- Cable Testing;
- 3rd Party Asset Crossings;
- Anchor Handling;
- Crew Transfer.
Cable Jointing:
- Remobilisation;
- Recovering of cables;
- Overboarding of Joint;
- Anchor Handling;
- Crew Transfer;
- Demobilisation plan.